Philadelphia, PA · Student housing

Evo at Cira Centre South

Student apartment install in Philadelphia, PA: sofas, chairs, loveseats and mattresses.

LocationPhiladelphia, PA
Project typeStudent housing
ClientSmarter Furnishings
DatesAugust 11 to 16, 2025
Crew13 BEAMM installers
Evo at Cira Centre South living room

How the job ran

A week before the crew arrived, the building flooded. Cleanup crews were still on site, the storage room was already full, and the install date did not move.

The single freight elevator broke down several times a day, 300 extra dining tables arrived with nowhere to put them, trucks showed up off schedule, and the install lists were missing or wrong. BEAMM tracked product by hand, built a working storage system for overstock and damaged pieces, and coordinated daily with the flood crews and property management.

Midweek, part of the crew was moved to a second project. The rest finished Evo on time without outside supervision.

  • Done by August 16, 2025 as planned
  • Every piece of freight installed or accounted for

What we installed

  • Sofas
  • Chairs
  • Loveseats
  • Mattresses
  • Task chairs
  • Side chairs
  • Counter tables

Have a job like this coming up?

Send the building, the scope and the dates. We’ll call you back about crew availability.

More student housing

The full job index