🛠️ BEAMM Case Study (Part 1) – SkyVue Install, Phase 1 (Pittsburgh, PA)
🏙 Project Snapshot
- Client: Smarter Furnishings
 - Property: SkyVue Apartments – Pittsburgh, Pennsylvania
 - Type: Full-service install of new furniture + storage phase
 - Scope: Multi-crew job with ongoing return scheduled
 - Duration: 5 working days
 - Crew:
- 5-person BEAMM team
 - Smarter Furnishings team (10–12, partially sent home)
 - Armstrong crew (8, exited before project wrapped)
 
 
✈️ Arrival After a Cross-Country Install
BEAMM arrived in Pittsburgh straight off a completed install at 13th & Olive in Eugene, Oregon.
We flew overnight, landed before sunrise, and showed up to site by late morning — running on time zone whiplash and no sleep.
Despite the travel, we worked until 9:00 PM that night and stayed past midnight the next.
The next day, we went back and kept moving — outpacing both crews already on-site.
🧱 Field Conditions
- Entered mid-install, no prep time
 - Long-distance hotel commute via Uber (no rental cars due to crew age)
 - 3 crews on-site at first: BEAMM, Smarter, Armstrong
 - Coordinated daily unloads of 2+ freight trucks
 - Handled wacky logistics:
- One day, 3 trucks arrived instead of 2
 - Another day, a truck showed up empty that was supposed to have inventory
 
 - Armstrong’s team exited early
 - Smarter reduced its crew size after seeing BEAMM’s efficiency
 - BEAMM operated with full autonomy
 
🏁 Floor Race (and Beatdown)
- BEAMM started from the top floor
 - Smarter’s crew started from the bottom floor
 - Unofficial challenge: race to the middle
 - Result? BEAMM reached the middle first with half the crew size
 - No corners cut. Just clean, complete installs
 
🛠 What BEAMM Delivered
- Multi-day install support from entry to completion
 - Clean staging, layout, and trash removal every floor
 - Adjusted to changing delivery schedules and inventory chaos
 - Stored remaining furniture onsite, prepped for future install
 - Zero corrections, no crew babysitting, no delays
 